HBP Ltd was appointed to deliver infrastructure works as part of the Devonshire Dock Quay (DDQ) extension, supporting the UK’s Dreadnought Submarine Programme at the live, secure site operated by BAE Systems in Barrow-in-Furness.
The contract included a package of enabling and support works essential to the safe expansion of the quay. Key deliverables included:
All works were delivered under our ISO 9001, 14001, and 45001-certified Integrated Management System. Our Operations Manager, Tom Butler, developed project-specific controls in collaboration with McLaughin & Harvey including a Quality Management Plan (QMP), Waste Management Plan (WMP), Traffic Management Plan, and detailed RAMS to ensure risks were managed and quality maintained throughout.
To address limited on-site storage and the demands of a live operational environment, we implemented a coordinated logistics strategy. This included upgrading our fleet with reversing cameras, deploying vehicle marshals, and introducing a priority traffic system. Daily collaborative logistics planning was coordinated with the client, other contractors and stakeholders.
Our WMP governed all soil movements. Excavated materials were WAC tested and classified, with hazardous waste removed under full consignment controls. To support client and project environmental objectives, we reprocessed inert arisings into CE/UKCA-certified 6N aggregate, which was tested weekly and monthly to meet design specifications.
High standards of health and safety were maintained through daily briefings, ongoing audits, and regular senior management tours.
No RIDDORs have been recorded to date, and consistent KPI compliance has led to further work being awarded under the infrastructure programme.
Our work at BAE Systems demonstrates our ability to deliver enabling and infrastructure works in constrained, live environments while maintaining programme, quality, and safety standards. This experience is directly relevant to Lot 3, where we expect to deliver public-facing civils schemes with similar logistical constraints. Our experience we will apply to Lot 3 includes:
HBP provided all plant, materials and logistics and rarely outsourced but when required we opted for local suppliers. Social value delivery was embedded into our operational model, using a trusted, Cumbrian-based supply chain for plant hire, materials, and logistics, keeping spend within the regional economy. We also donated time to support local VCSEs including a charity golf day for St Mary’s Hospice and donating to local food banks during the Christmas period. Also, the Cumbrian Challenge to raise money for walking with the wounded.